Contracts     Design/Build     Dispute Resolution

Contracts
Contract Review and Risk Allocation
   Interpreting Contracts
   Risk Management
   Standard Contracts

Negotiation Skills and Strategies

Contract Management
   Contract Administration
   Change Management

Lessons Learned

Contract Administration Tools
   Municipal Rehab Project Tools
   International Design-Build Tools

Lessons Learned

The following Lessons Learned are case studies from CSG files. There is much to be learned from our experiences- the exemplary, the mundane, and the disastrous.

Our Workshops incorporate a Lessons Learned segment that requires the participation of senior personnel, who share their own lessons learned along the workshop topic. This sharing of real life experiences resonates with workshop participants and is always the most highly rated portion of our workshops.

The following five Lessons Learned will be regularly updated, as there are more experiences to share than this space allows. Please contact us if you would like notification when these updates occur. We also welcome your suggestions and requests for topics you would like to see covered. Please also feel free to share your own Lessons Learned.

Lesson Learned #1.  Confidentiality Obligations
--
Two separate offices of a management consulting firm had been retained by different parties in a hotly contested rate proceeding before a state Public Utilities Commission. The two clients had potentially adverse interests to each other. Each office of the management consulting firm recognized the potential individual conflict of interest situation if individuals worked on both engagements. However any potential organizational conflict of interest was not addressed or discussed with either client.
--
As a result of a client concern, the management consulting firm was requested to terminate its contract valued at approximately one million dollars with the other client, based on ethical obligations and conflict of interest.
--
CSG consultants assisted the management consulting firm in negotiating an acceptable confidentiality agreement and conflict of interest mitigation plan that met the requirements of both clients and preserved the one million dollar contract.
--
Lesson Learned:  Any consideration of conflict of interests and confidentiality obligations should take into account both personal and organizational conflicts of interest. When perceived conflicts of interest may arise, it is critical to develop mitigation strategies that address any potential developing conflict of interest to avoid ethical problems and potential termination of a contract.
--
--
--

--

Lesson Learned #2.  Recovery of Payment Overruns
--
A client was involved in an administrative proceeding with a committee of attorneys providing the project management. A consulting firm had a contract with this client to provide technical consulting to the client’s attorneys. The consultant’s proposal provided an estimate of total cost of services, based upon the consultant’s experience on similar proceedings. A number of assumptions were incorporated into the development of the consultant’s cost estimate, but those assumptions were not specifically provided for or discussed with the client.
--
The consultant’s project manager did not regularly communicate with his client regarding the actual and projected level of effort on various tasks being performed. The consultant project manager failed to provide notice as required under the contract when any specific task level of effort was projected to exceed the estimate set forth in the contract. The work was finally completed with the consultant having provided approximately $250,000 or 25% of additional services in excess of any authorized amounts.
--
Although the consultant established that its services were completely responsive to all changing conditions of the client and its legal counsel and the consultant’s services resulted in savings of tens of millions of dollars to the client, the consultant’s failure to comply with contract notice requirements and its failure to keep the client regularly informed as to levels of effort on each task, resulted in the failure of the consultant to recover most of its cost overruns.
--
CSG consultants were asked to assist in developing a negotiating strategy and cost recovery plan after the cost overrun had occurred and the work had been completed. Arbitration and mediation alternatives were evaluated and incorporated into the negotiation plan. The negotiation strategy focused on early resolution of the dispute between senior management. The negotiation strategy was successful in recovering a portion of the disputed amount.

--
Lesson Learned:  The consultant failed to explain to its client the underlying assumptions that formed the basis of its cost estimate. The consultant also failed to advise its client regarding the changing requests and project conditions and how those changes affected its actual and projected levels of effort. Finally the consultant failed to comply with straightforward contract notice requirements that would allow the client to allocate funding and establish priorities for its remaining work. A negotiation strategy was developed that addressed the client project management issues with his poor management of the changing work. Because the consultant's project manager was too busy on technical work to administer the contract, the contract management should have been delegated to a contract administrator.
--
As consultants frequently discover, clients are rarely happy to pay surprise additional amounts at the end of project, regardless of the excellent results provided by the consultant.
--
--
--

--
Lesson Learned #3.  Site Safety
--
A construction management contract included specific limitations that the CM had no responsibility for site safety compliance by the construction contractors. The construction contracts also provided that the contractors were exclusively responsible for site safety compliance. However, CM representatives on a regular basis reviewed and confirmed compliance with various safety requirements by the contractor. A serious site accident occurred and the CM was sued by the injured worker.
--
The matter was litigated and the court held that the actions of the CM in actually reviewing and confirming compliance by the contractor with its safety requirements established a legal obligation upon which the injured worker could successfully recover damages. The court held the actions of the CM provided a legal basis for liability, even though the actions were inconsistent with the CM’s written scope of work.
--
Lesson Learned:  Actions by field personnel can supersede or modify any contractual provisions with respect to site safety or other construction phase requirements. Field personnel should be trained to avoid actions that will be construed as assuming partial responsibility for site safety or other contractor obligations.
--

--
--
--

--
Lesson Learned #4.  Recovery of Payment
--
An engineering firm had contracted with a foreign company to provide professional services without securing any payment security in the form of letter of credit, advance payments, or other customary payment security used in international contracting. As is customary in some business cultures, the final invoice was not paid when due. The project managers for the client and engineering company did not communicate well regarding the status of the past due payment, resulting in the amount becoming seriously past due. The past due payment matter was referred to outside counsel for initiation of collection activities.
--
Outside counsel first sent a simple letter confirming the amount due and describing the additional attorneys fees and costs that would be recoverable from the client if arbitration proceedings were required. As result of the single letter, the client discovered the missing invoice" and made prompt payment of the full amount due.
--
Lesson Learned:  The engineering firm did not have in place a process or check list for confirming that regular communications were occurring with the client regarding payment issues. The firm also did not use multiple levels of contact with the client when payment questions arose. Finally, clear contractual rights for prompt arbitration resolution and recovery of attorneys fees by the prevailing party resulted in prompt payment of the "missing" invoice.
--

--
--
--

--
Lesson Learned #5.  Incorporating Proposal into Contract
--
An engineering firm prepared a proposal as part of a competitive negotiation on a major infrastructure project with engineering fees in excess of $10 million. The proposal outlined an extensive quality management program that could be implemented by the client in managing its substantial construction effort.
--
During the course of contract negotiations and the performance of the engineering contract, the client decided to not implement any of the extensive quality management options set forth in the proposal. However, the proposal was incorporated into the contract without any revision or exception. During contract performance, major problems arose on the construction contracts due to poor quality management being performed by the construction contractors.
--
The dispute lead to major multi-party litigation. The client attempted to recover all damages arising from poor contractor performance from the engineering firm because the engineering firm had breached its contractual obligation to provide the extensive quality management program set forth in its proposal.
--
The engineering firm had no documentation of client direction or record of negotiation indicating that the client had requested changes to the proposed quality management program in the proposal. To compound the problem, the client had requested that essentially all project management and contract administration activities be performed verbally or informally, so the engineering firm project team had few documents confirming client directions.
--
The engineering firm was forced to defend litigation in excess of $35 million in claims. The firm did settle the litigation in the mid-seven figures, due in part to the uncertainty of its actual scope of work created by the incorporation of the proposal.
--
Lesson Learned:  Proposals or any portion of the proposal should not be incorporated into the final negotiating contract, without careful review and confirmation that the portion of the proposal being incorporated is appropriate for contract purposes. Proposals often use marketing language that is inappropriate for contract specification and scope of work purposes.
--
An important role of a project manager is to manage client relationships in an appropriate manner and to document client negotiations and directions regarding changes in the scope of work.
--
On technically complex and fast-moving projects, client communication and documentation of client directions are often sacrificed in order to perform the technical work. Lack of documentation confirming verbal or informal directions is a frequent basis for claims and loss of revenue.
--
--
--



TOP

 

  -- Home  |   Workshops/Seminars  |  Live Web Conferences   |   Self Study Programs   |   Continuing Education Credits --
-- Faculty | Consulting | News | About CSG | Privacy | Contact Us

Copyright © 2005 Contract Solutions Group
P.O. Box 775    Vashon Island, WA 98070    (206) 463-7487     Fax - (206) 463-7488
Design by Sage Studio

webconference about